On June 25, 2019, there was a signing ceremony for the construction of the National Highway No. 2 and No. 22 Improvement Project between Ministry of Public Works and Transport and Hanshin Engineering and Construction Co., Ltd. .
According to Sun Chanthol, Minister of Public Works and Transport, in the signing ceremony, the project is divided into three sections, including:
1 . From the roundabout of Ta khmao to the roundabout of rice paddy It stretches over 8 kilometers, extending into 4 orbits, 15 meters for urban areas and 20.5 meters outside the town.
2. From the roundabout of rice paddy circle to the roundabout O Chambok near Takeo Province 53.8 km long The pavement are two orbit and 13 meters wide.
3. National Road No. 22 from O Chambok to The Ang Tasaom Market is more than 9 km. The total length of this project is 72 km.
The deal is expected to receive loans from the Korean side, which is set to spend $ 45.7 million without a $ 8 million reserve. And this route will be constructed by the end of 2019 and will take 30 months to complete.This news from business-cambodia.com
Disclaimer: The re-forward articles on Compass website are for the purpose of conveying more information, and it does not mean that the Compass website agrees with its views or confirms the authenticity of its content. Article noted as "Source: Compass original", please note that the source from Compass. The content of the article is for reference only and should not consider as investment advice, and it does not mean that Compass agree with its views.
0
()
Application has been successfully submitted
we will contact you soon, please pay attention
Call:+855 66300666
+855 (0) 23222206 (CN/EN/KH)
+86 023 67480241 (CN)
+855 (0) 66400666 (CN/EN/KH)